An adapted constraint-programming formulation of the resource-constrained project scheduling problem applied to the identical parallel machines group shop and mixed shop scheduling problems
Year of publication: |
2025
|
---|---|
Authors: | Yuraszeck, Francisco ; Mejía, Gonzalo ; Lüer-Villagra, Armin |
Published in: |
International transactions in operational research : a journal of the International Federation of Operational Research Societies. - Oxford : Wiley-Blackwell, ISSN 1475-3995, ZDB-ID 2019815-2. - Vol. 32.2025, 3, p. 1422-1441
|
Subject: | constraint programming | group shop | job shop | mixed shop | open shop | parallel machines | resource-constrained project scheduling | stage shop | Scheduling-Verfahren | Scheduling problem | Theorie | Theory | Konsumentenverhalten | Consumer behaviour | Projektmanagement | Project management | Produktionssteuerung | Production control | Einzelhandel | Retail trade | Einkaufszentrum | Shopping center |
-
Naderi, Bahman, (2023)
-
The three-machine proportionate open shop and mixed shop minimum makespan problems
Koulamas, Christos, (2015)
-
Pempera, Jaroslaw, (2018)
- More ...
-
A constraint programming-based lower bounding procedure for the job shop scheduling problem
Yuraszeck, Francisco, (2025)
-
Mejía, Gonzalo, (2023)
-
Mejía, Gonzalo, (2020)
- More ...