We review the well-known RSM priority rule to solve the resource constrained project scheduling problem. A detailed analysis of this rule reveals that it is based on assumptions which do not hold in general and hence might lead to poor solutions. Consequently, an improved RSM priority rule is...
Persistent link: https://www.econbiz.de/10011739746
Persistent link: https://www.econbiz.de/10011735573
Persistent link: https://www.econbiz.de/10014022097
The problem of scheduling multiple, large scale, make-to-order assemblies is considered. Beside "classical" precedence- and resource constraints as known from resource constrained project scheduling we take spatial resource and part availability constraints into account. The objective is to...
Persistent link: https://www.econbiz.de/10011558728
We consider the problem of scheduling multiple, large-scale, make-to-order assemblies under resource, assembly area, and part availability constraints. Such problems typically occur in the assembly of high volume, discrete make-to-order products. Based on a list scheduling procedure which has...
Persistent link: https://www.econbiz.de/10011558732
In machine tool assembly several make-to-order products have to be manufactured simultaneously in a multi-stage production system. Due to customer requirements batches are very small. A process plan specifies the neccessary machines, tools, auxiliary devices as well as the operations to be...
Persistent link: https://www.econbiz.de/10011613744
We review the well-known RSM priority rule to solve the resource constrained project scheduling problem. A detailed analysis of this rule reveals that it is based on assumptions which do not hold in general and hence might lead to poor solutions. Consequently, an improved RSM priority rule is...
Persistent link: https://www.econbiz.de/10011613747
In this paper we propose a new heuristic to solve the well-known multiple resource-constrained project scheduling problem. The method is basically a biased random sampling procedure which shows extremely good results by use of the following features: A problem-based selection of the solution...
Persistent link: https://www.econbiz.de/10011613750
This paper addresses a general class of nonpreemptive resource-constrained project scheduling problems in which activity durations are discrete functions of committed renewable and nonrenewabe resources. We provide a 0-1 problem formulation and stress the importance of the outlined model by...
Persistent link: https://www.econbiz.de/10011613754
Produktionsplanungs- und -steuerungssysteme (PPS-Systeme) haben in den letzten Jahren in der wissenschaftlichen Literatur und der betrieblichen Praxis starke Beachtung gefunden. Während diese Systeme die Problematik der (Groß-) Serienfertigung (einigermaßen) bewältigen, sind sie für die...
Persistent link: https://www.econbiz.de/10011653571