City gas distribution projects delay in India : a critical assessment of risks
Purpose: This study aims to identify and rank the operational and financial risks causing a delay in the commencement of the city gas distribution project in India. Design/methodology/approach: This study reviews the literature to identify operational and financial risks variables associated with infrastructure projects. Followed by a survey to isolate and assess the critical risk factors for city gas distribution network project in India. The survey data is evaluated using factor analysis to understand the latent structure of the critical risk factors. Second, the author ranks the identified variables as per significance by using the mean score method. Findings: Five critical risk factors with 20 variables were extracted and assessed to build more understanding of their significance and impact on city gas distribution network project. Originality/value: This study is the first attempt to follow the management approach to identify and rank operational and financial risks impacting city gas distribution project.
Year of publication: |
2021
|
---|---|
Authors: | Rawat, Atul ; Gupta, Sumeet ; Rao, T. Joji |
Published in: |
International Journal of Energy Sector Management. - Emerald, ISSN 1750-6220, ZDB-ID 2280261-7. - Vol. 15.2021, 6 (09.06.), p. 1163-1180
|
Publisher: |
Emerald |
Saved in:
Saved in favorites
Similar items by person
-
Rawat, Atul, (2023)
-
Risk analysis and mitigation for the city gas distribution projects
Rawat, Atul, (2021)
-
Modeling the strategies to accelerate the natural gas business market growth in a developing country
Rawat, Atul, (2023)
- More ...