In recent years, new resource types have been established in project scheduling. These include so-called partially renewable resources, whose total capacity applies only to a subset of periods in the planning horizon. In this paper, we consider the extension of the resource-constrained project...
Persistent link: https://www.econbiz.de/10015371251
In this paper, we consider a resource overload problem and add a tardiness penalty to the objective function when a prescribed project makespan is exceeded, which enables a trade-off between a balanced resource utilization and a project delay. For the tardiness penalty, we distinguish between a...