Showing 1 - 10 of 34
We investigate two scheduling problems. The first is scheduling with agreements (SWA) that consists in scheduling a set of jobs non-preemptively on identical machines in a minimum time, subject to constraints that only some specific jobs can be scheduled concurrently. These constraints are...
Persistent link: https://www.econbiz.de/10011097771
In this paper we propose a heuristic for solving the problem of resource constrained preemptive scheduling in the two-stage flowshop with one machine at the first stage and parallel unrelated machines at the second stage, where renewable resources are shared among the stages, so some quantities...
Persistent link: https://www.econbiz.de/10010753509
We consider a make-to-order (MTO) manufacturer who has won multiple contracts with specified quantities to be delivered by certain due dates. Before production starts, the company must configure its supply chain and make sourcing decisions. It also needs to plan the starting time for each...
Persistent link: https://www.econbiz.de/10010597569
This paper introduces a multi-project problem environment which involves multiple projects with assigned due dates; activities that have alternative resource usage modes; a resource dedication policy that does not allow sharing of resources among projects throughout the planning horizon; and a...
Persistent link: https://www.econbiz.de/10011097731
We consider project scheduling where the project manager’s objective is to minimize the time from when an adversary discovers the project until the completion of the project. We analyze the complexity of the problem identifying both polynomially solvable and NP-hard versions of the problem....
Persistent link: https://www.econbiz.de/10011097801
This paper addresses the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP). Such a problem often arises in many real-world applications, in which the resource usage of an activity is not merely constant, but can be adjusted from period to period. The FRCPSP...
Persistent link: https://www.econbiz.de/10011097852
We consider a continuous time–cost tradeoff problem with multiple milestones and completely ordered jobs. If a milestone is tardy, a penalty cost may be imposed. The processing times of jobs can be compressed by additional resources or activities that incur compression costs. The objective is...
Persistent link: https://www.econbiz.de/10011264308
We propose a new mixed integer programming formulation and solution algorithm for a multi-mode resource-constrained project scheduling problem with availability constraints (calendars) and the objective to minimize the resource availability cost. Our model exploits the problem structure and has...
Persistent link: https://www.econbiz.de/10011264341
In this paper we address the Preemptive Resource Constrained Project Scheduling Problem (PRCPSP). PRCPSP requires a partially ordered set of activities to be scheduled using limited renewable resources such that any activity can be interrupted and later resumed without penalty. The objective is...
Persistent link: https://www.econbiz.de/10011209345
In this paper, we address the issue of optimal selection of portfolio of projects using reinvestment strategy within a flexible time horizon. We assume that an investor intends to invest his/her initial capital on the implementation of some projects in a flexible time horizon. The investor’s...
Persistent link: https://www.econbiz.de/10011209412