One of the financing schemes in providing an infrastructure project is a public-private-partnership (PPP). PPP is an implementation option and infrastructure service that provides incremental benefits as well as private financing access to promote the government. This study aims to provide a new...
Persistent link: https://www.econbiz.de/10014106298
In greenfield toll-road projects, financial sustainability has been a major issue. Many toll roads cannot be operated. Although most of Indonesia's 24 toll road concessions have already been signed by the Toll Road Authority, most of them were caused by financing problems. Three problems have...
Persistent link: https://www.econbiz.de/10012888918
Persistent link: https://www.econbiz.de/10009511038
There are three main problems in Indonesia toll road financing model. First, it is the lack of state budget and delayed funding distribution for land acquisition. The second problem is the lack of financial ability of the winning company which leads to financial closing failure. The third...
Persistent link: https://www.econbiz.de/10012870811
One of the largest impediments to toll road development is land acquisition. In an ideal perspective, the required land should be acquired before a toll road project begins. However, the reality often does not meet the expectation. The government, which should accept the liability in the first...
Persistent link: https://www.econbiz.de/10012870835
The financial sustainability has been a major issue in greenfield toll-road projects. Most of Indonesia's 24 toll road concessions already signed by Toll Road Authority, for instance, cannot be put in operation because of financing problems. Uncertainties of long-term project revenues,...