Showing 1 - 10 of 47
In this paper we study the resource-constrained project-scheduling problem with discounted cash flows. Each activity of this resource-constrained project-scheduling problem has certain resource requirements and a known deterministic cash flow that can be either positive or negative....
Persistent link: https://www.econbiz.de/10009209200
Persistent link: https://www.econbiz.de/10005329845
Persistent link: https://www.econbiz.de/10005109203
Persistent link: https://www.econbiz.de/10005339638
Persistent link: https://www.econbiz.de/10005347498
Persistent link: https://www.econbiz.de/10005347909
Solution-robust project scheduling is a growing research field aiming at constructing proactive schedules to cope with multiple disruptions during project execution. When stochastic activity durations are considered, including time buffers between activities is a proven method to improve the...
Persistent link: https://www.econbiz.de/10005253016
In this paper a branch-and-bound procedure is described for scheduling the activities of a project of the PERT/CPM variety subject to precedence and resource constraints where the objective is to minimize project duration. The procedure is based on a depth-first solution strategy in which nodes...
Persistent link: https://www.econbiz.de/10009198063
The resource-constrained project scheduling problem involves the determination of a schedule of the project activities, satisfying the precedence and resource constraints while minimizing the project duration. In practice, activity durations may be subject to variability. We propose a stochastic...
Persistent link: https://www.econbiz.de/10009146085
The majority of publications in the extensive literature on resource-constrained project scheduling focus on a static deterministic setting for which a so-called baseline schedule is computed prior to project execution. In the real world, however, a project may be subject to considerable...
Persistent link: https://www.econbiz.de/10010693718