A heuristic procedure to solve the project staffing problem with discrete time/resource trade-offs and personnel scheduling constraints
Year of publication: |
January 2019
|
---|---|
Authors: | Van Den Eeckhout, M. ; Maenhout, B. ; Vanhoucke, Mario |
Published in: |
Computers & operations research : and their applications to problems of world concern ; an international journal. - Oxford [u.a.] : Elsevier, ISSN 0305-0548, ZDB-ID 194012-0. - Vol. 101.2019, p. 144-161
|
Subject: | Multi-mode project scheduling | Personnel staffing | Heuristic optimisation | Scheduling-Verfahren | Scheduling problem | Projektmanagement | Project management | Heuristik | Heuristics | Personalmanagement | Human Resource Management | Theorie | Theory | Personaleinsatzplanung | Crew scheduling | Personalauswahl | Personnel selection |
-
Van Den Eeckhout, M., (2021)
-
The bilevel optimisation of a multi-agent project scheduling and staffing problem
Milička, P., (2022)
-
Multisite and multishift personnel planning with set-up costs
Nearchou, A. C., (2020)
- More ...
-
Van Den Eeckhout, M., (2020)
-
Van Den Eeckhout, M., (2021)
-
The bilevel optimisation of a multi-agent project scheduling and staffing problem
Milička, P., (2022)
- More ...